Indio prepares to roll out fiber broadband internet to three mobile home parks
Following a citywide expansion of fiber lines along major streets, Indio engineers are preparing to connect individual mobile homes starting this fall.

The Indio Mobile Home Fair Practices Commission received an update last week on the city’s fiber optic broadband plan, which will bring internet service to three mobile home parks: Arabian Gardens, Towne Mobile Homes and Indian Wells.
Don Ueno, with the city’s engineering department, told commissioners the $8 million grant is being used to bring broadband to disadvantaged and underserved communities, many of which are located in mobile home parks.
The city has already used a portion of the funding to install fiber backbone infrastructure along arterial streets including Jefferson Street, Highway 111 and Jackson Street. The next phase will extend that infrastructure from those streets into the mobile home parks and connect it to individual homes.
The city is partnering with a company called Onward to provide the service, “Onward is going to be cheaper than the usual Frontier Verizon and AT&T,” he said. Mobile home residents can expect to pay about $30 a month compared to $35 to $40 from other companies.
Ueno said connecting to the service will not be mandatory for residents once the infrastructure is in place and installation is expected between October and March.
Ueno told commissioners the city initially worked with a different partner after receiving the grant, but that company backed out after performing a due diligence review. The city then interviewed six companies to replace it, “For whatever reason, one by one, they all made the tough decision that it didn’t pencil out for them,” he said.
In response to a commissioner’s question, Ueno said the city considered both economically disadvantaged census tracts and areas lacking broadband access, using Federal Communications Commission mapping data that showed unconnected households concentrated in mobile home parks.
Other mobile home parks were contacted about participating but did not reach agreements with the city, in part due to their distance from the existing fiber backbone, Ueno said.
Asked about the potential cost for residents to connect once infrastructure is installed, Ueno said he did not have an estimate for installation fees but reiterated the target monthly service cost of $30.